1
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A construction project consists of twelve activities. The estimated duration (in days) required
to complete each of the activities along with the corresponding network diagram is shown
below.
Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,
Questions Asked from Critical Path Method (Marks 1)
Number in Brackets after Paper Indicates No. of Questions
GATE CE Subjects
Construction Material and Management
Geomatics Engineering Or Surveying
Engineering Mechanics
Transportation Engineering
Strength of Materials Or Solid Mechanics
Reinforced Cement Concrete
Steel Structures
Environmental Engineering
Engineering Mathematics
Structural Analysis
Geotechnical Engineering
Fluid Mechanics and Hydraulic Machines
General Aptitude