A construction project consists of twelve activities. The estimated duration (in days) required to complete each of the activities along with the corresponding network diagram is shown below. GATE CE 2016 Set 2 Construction Material and Management - Critical Path Method Question 8 English Total floats (in days) for the activities 5-7 and 11-12 for the project are, respectively,
A
25 and 1
B
1 and 1
C
0 and 0
D
81 and 0