1
GATE CE 2024 Set 1
MCQ (Single Correct Answer)
+1
-0.33

The following figure shows the arrangement of formwork for casting a cantilever RC beam.

GATE CE 2024 Set 1 Reinforced Cement Concrete - Workmenship and Fundamentals Question 2 English

The correct sequence of removing the Shores/Props is:

A

S1 → S2 → S3 → S4 → S5

B

S5 → S4 → S3 → S2 → S1

C

S3 → S2 → S4 → S1 → S5

D

S3 → S4 → S2 → S5 → S1

2
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Let the characteristic strength be defined as that value, below which not more than 50% of the results are expected to fall. Assuming a standard deviation of 4 MPa, the target mean strength (in MPa) to be considered in the mix design of a M25 concrete would be
A
18.42
B
21.00
C
25.00
D
31.58
3
GATE CE 2015 Set 1
MCQ (Single Correct Answer)
+1
-0.3
Consider the following statements for air-entrained concrete:

(i) Air-entrainment reduces the water demand for a given level of workability

(ii) Use of air-entrained concrete is required in environments where cyclic freezing and thawing is expected.

Which of the following is TRUE?
A
Both (i) and (ii) are True
B
Both (i) and (ii) are False
C
(i) is True and (ii) is False
D
(i) is False and (ii) is True
4
GATE CE 2015 Set 1
MCQ (Single Correct Answer)
+1
-0.3
Workability of concrete can be measured using slump, compaction factor and Vee bee time. Consider the following statements for workability of concrete:

(i) As the slump increases, the Vebe time increases

(ii) As the slum increases, the compaction factor increases

Which of the following is TRUE?
A
Both (i) and (ii) are True
B
Both (i) and (ii) are False
C
(i) is True and (ii) is False
D
(i) is False and (ii) is True
GATE CE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12