1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider the following data for an item.
Annual demand: $$2500$$ units per year Ordering cost: Rs.100 per order Inventory holding rate: $$25\% $$ of unit price. The optimum order quantity (in units) is:

Price quoted by a supplier

GATE ME 2006 Industrial Engineering - Inventory Control Question 20 English

The optimum order quantity (in units) is

A
$$447$$
B
$$471$$
C
$$500$$
D
$$ \ge 600$$
2
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 22 English

The standard deviation of the critical path of the project is

A
$$\sqrt {151} $$ days
B
$$\sqrt {155} $$ days
C
$$\sqrt {200} $$ days
D
$$\sqrt {238} $$ days
3
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
The table gives details of an assembly line. GATE ME 2006 Industrial Engineering - Line Balancing Question 1 English

What is the line efficiency of the assembly line?

A
$$70\% $$
B
$$75\% $$
C
$$80\% $$
D
$$85\% $$
4
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 23 English

The expected completion time of the project is

A
$$238$$ days
B
$$224$$ days
C
$$171$$ days
D
$$155$$ days