1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 20 English

The expected completion time of the project is

A
$$238$$ days
B
$$224$$ days
C
$$171$$ days
D
$$155$$ days
2
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 19 English

The standard deviation of the critical path of the project is

A
$$\sqrt {151} $$ days
B
$$\sqrt {155} $$ days
C
$$\sqrt {200} $$ days
D
$$\sqrt {238} $$ days
3
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
The table gives details of an assembly line. GATE ME 2006 Industrial Engineering - Line Balancing Question 1 English

What is the line efficiency of the assembly line?

A
$$70\% $$
B
$$75\% $$
C
$$80\% $$
D
$$85\% $$
4
GATE ME 2006
MCQ (Single Correct Answer)
+1
-0.3
The number of customers arriving at a railway reservation counter is Poisson distributed with an arrival rate of eight customers per hour. The reservation clerk at this counter takes six minutes per customer on an average with an exponentially distributed service time. The average number of the customers in the queue will be.
A
$$3$$
B
$$3.2$$
C
$$4$$
D
$$4.2$$
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12