1
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
A stockist wishes to optimize the number of perishable items he needs to stock in any month in his store. The demand distribution for this perishable item is: GATE ME 2006 Industrial Engineering - Inventory Control Question 18 English The stockist pays Rs.$$70$$ for each item and he sells each at Rs.$$90.$$ if the stock is left unsold in any month, he can sell the item at Rs.$$50$$ each. There is no penalty for unfulfilled demand. To maximize the expected profit, the optimal stock level is:

A
$$5$$ units
B
$$4$$ units
C
$$3$$ units
D
$$2$$ units
2
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 22 English

The expected completion time of the project is

A
$$238$$ days
B
$$224$$ days
C
$$171$$ days
D
$$155$$ days
3
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
Consider a $$PERT$$ network for a project involving six tasks ($$a$$ to $$f$$) GATE ME 2006 Industrial Engineering - Pert and Cpm Question 21 English

The standard deviation of the critical path of the project is

A
$$\sqrt {151} $$ days
B
$$\sqrt {155} $$ days
C
$$\sqrt {200} $$ days
D
$$\sqrt {238} $$ days
4
GATE ME 2006
MCQ (Single Correct Answer)
+2
-0.6
The table gives details of an assembly line. GATE ME 2006 Industrial Engineering - Line Balancing Question 1 English

What is the line efficiency of the assembly line?

A
$$70\% $$
B
$$75\% $$
C
$$80\% $$
D
$$85\% $$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12