1
GATE EE 2011
MCQ (Single Correct Answer)
+2
-0.6
A solar energy installation utilize a three – phase bridge converter to feed energy into power system through a transformer of $$400V/400 V,$$ as shown below. The energy is collected in a bank of $$400$$ $$V$$ battery and is connected to converter through a large filter choke of resistance $$10\Omega $$. GATE EE 2011 Power Electronics - Single and Three Phase Rectifier Question 29 English

The maximum current through the battery will be

A
$$14$$ $$A$$
B
$$40$$ $$A$$
C
$$80$$ $$A$$
D
$$94$$ $$A$$
2
GATE EE 2011
MCQ (Single Correct Answer)
+2
-0.6
A voltage commutated chopper circuit, operated at $$500Hz,$$ is shown below. If the maximum value of load current is $$10A,$$ then the maximum current through the main $$(M)$$ and auxiliary $$(A)$$ thyristors will be GATE EE 2011 Power Electronics - Choppers and Commutation Techniques Question 27 English
A
$${i_{M\max }} = 12\,A$$ and $$\,{i_{A\max }} = 10\,A$$
B
$${i_{M\max }} = 12\,A$$ and $$\,{i_{A\max }} = 2\,A$$
C
$${i_{M\max }} = 10\,A$$ and $$\,{i_{A\max }} = 12\,A$$
D
$${i_{M\max }} = 10\,A$$ and $$\,{i_{A\max }} = 8\,A$$
3
GATE EE 2011
MCQ (Single Correct Answer)
+1
-0.3
A three-phase current source inverter used for the speed control of an induction motor is to be realized using MOSFET switches as shown below. Switches $${S_1}$$ to $${S_6}$$ are identical switches. GATE EE 2011 Power Electronics - Inverters Question 27 English

The proper configuration for realizing switches $${S_1}$$ to $${S_6}$$ is

A
GATE EE 2011 Power Electronics - Inverters Question 27 English Option 1
B
GATE EE 2011 Power Electronics - Inverters Question 27 English Option 2
C
GATE EE 2011 Power Electronics - Inverters Question 27 English Option 3
D
GATE EE 2011 Power Electronics - Inverters Question 27 English Option 4
4
GATE EE 2011
MCQ (Single Correct Answer)
+2
-0.6
Two generator units $$G1$$ and $$G2$$ are connected by $$15$$ $$kV$$ line with a bus at the mid-point as shown below GATE EE 2011 Power System Analysis - Per Unit System Question 5 English
$${G_1} = 250\,\,MVA.\,\,\,15kV,\,\,$$ positive sequence $$X = 25$$% on its own base
$${G_2} = 100\,\,MVA.\,\,\,15kV,\,$$ positive sequence $$X = 10$$% on its own base
$${L_1}$$ and $${L_2}$$ $$= 10$$ $$km,$$ positive sequence $$ X = 0.225$$ $$\,\,\Omega /km$$

For the above system, the positive sequence diagram with the p.u values on the $$100$$ $$MVA$$ common

A
GATE EE 2011 Power System Analysis - Per Unit System Question 5 English Option 1
B
GATE EE 2011 Power System Analysis - Per Unit System Question 5 English Option 2
C
GATE EE 2011 Power System Analysis - Per Unit System Question 5 English Option 3
D
GATE EE 2011 Power System Analysis - Per Unit System Question 5 English Option 4
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12