1
GATE CE 2017 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Given that the scope of the construction work is well-defined with all its drawings, specifications, quantities and estimates, which one of the following types of contract would be most preferred?
A
EPC contract
B
Percentage rate contract
C
Item rate contract
D
Lump sum contract
2
GATE CE 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
As per Indian standards for bricks, minimum acceptable compressive strength of any class of burnt clay bricks in dry state is
A
10.0MPa
B
7.5MPa
C
5.0MPa
D
3.5MPa
3
GATE CE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
Bull's trench kiln is used in the manufacturing of
A
Lime
B
Cement
C
Bricks
D
none of these
4
GATE CE 2016 Set 1
MCQ (Single Correct Answer)
+1
-0.3
The compound which is largely responsible for initial setting and early strength gain of Ordinary Portland Cement is
A
$$C_3A$$
B
$$C_3S$$
C
$$C_2S$$
D
$$C_4AF$$
GATE CE Subjects
Fluid Mechanics and Hydraulic Machines
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
CBSE
Class 12