1
GATE EE 1999
MCQ (Single Correct Answer)
+2
-0.6
A 3-phase, 11 kV, 50 Hz, 200 kW load has a power factor of 0.8 lag. A delta connected 3-phase capacitor is used to improve the power factor to unity. The capacitance power phase of the capacitor in micro-farads is
A
3.948
B
1.316
C
0.439
D
11.844
2
GATE EE 1999
MCQ (Single Correct Answer)
+2
-0.6
A single phase AC distributor supplies two single phase loads as shown in figure. The voltage drop from A to C is GATE EE 1999 Power System Analysis - Parameters and Performance of Transmission Lines Question 51 English
A
4.5 V
B
31.5 V
C
30 V
D
20 V
3
GATE EE 1999
MCQ (Single Correct Answer)
+2
-0.6
$$A$$ $$220$$ kV, $$20$$ km long, $$3$$-phase transmission line has the following $$A, B, C, D$$ constants. $$A=D=0.96$$$$\angle {3^0},$$ $$\,B = 55\angle {65^0}\,\,\Omega /$$ phase, $$\,C = 0.5 \times {10^{ - 4}}\angle {90^0}\,\,$$ $$S/$$phase. Its correct charging current per phase is
A
$$11/\sqrt 3 \,\,A$$
B
$$11$$ $$A$$
C
$$220$$ $$A$$
D
$$220/\sqrt 3 A.$$
4
GATE EE 1999
Subjective
+5
-0
A 66 kV, 3-phase, 50 Hz, 150 km long overhead transmission line is open circuited at the receiving end. Each conductor has a resistance of 0.25$$\Omega $$/km, an inductive reactance of 0.5$$\Omega $$/km and a capacitive admittance to neutral of 0.04 $$ \times $$ 10-4 S/km.

(a) Draw the nominal π-equivalent circuit and indicate the value of each parameter.
(b) Calculate the receiving end voltage if the sending end voltage is 66 kV.

EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering