GATE EE 1999
MCQ (Single Correct Answer)
+2
-0.6
$$A$$ $$220$$ kV, $$20$$ km long, $$3$$-phase transmission line has the following $$A, B, C, D$$ constants. $$A=D=0.96$$$$\angle {3^0},$$ $$\,B = 55\angle {65^0}\,\,\Omega /$$ phase, $$\,C = 0.5 \times {10^{ - 4}}\angle {90^0}\,\,$$ $$S/$$phase. Its correct charging current per phase is
A
$$11/\sqrt 3 \,\,A$$
B
$$11$$ $$A$$
C
$$220$$ $$A$$
D
$$220/\sqrt 3 A.$$
2
GATE EE 1999
Subjective
+5
-0
A 66 kV, 3-phase, 50 Hz, 150 km long overhead transmission line is open circuited at the receiving end. Each conductor has a resistance of 0.25$$\Omega $$/km, an inductive reactance of 0.5$$\Omega $$/km and a capacitive admittance to neutral of 0.04 $$ \times $$ 10-4 S/km.

(a) Draw the nominal π-equivalent circuit and indicate the value of each parameter.
(b) Calculate the receiving end voltage if the sending end voltage is 66 kV.

3
GATE EE 1999
Subjective
+5
-0
A 6.6 kV, 50 Hz single core lead sheathed cable has the following data:
Conductor diameter: 1.5 cm, length: 4 km. Internal diameter of the sheath : 3 cm
Resistivity of insulation : 1.3 $$ \times $$ 1012 $$\Omega $$-m. Relative permittivity of insulation : 3.5 Calculate

(a) the insulation resistance
(b) the capacitance and
(c) the maximum electric stress in the insulation

4
GATE EE 1999
MCQ (Single Correct Answer)
+2
-0.6
An industrial consumer has a daily load pattern of $$2000$$ $$kW$$, $$0.8$$ lag for $$12$$ Hrs. and $$1000$$ $$kW$$ $$UPF$$ for $$12$$ Hrs. The load factor is
A
$$0.5$$
B
$$0.75$$
C
$$0.6$$
D
$$2.0$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12