1
GATE EE 2007
MCQ (Single Correct Answer)
+2
-0.6
Suppose we define a sequence transformation between ''a-b-c'' and ''p-n-0''' variables as follows:
$$\left[ {\matrix{ {{f_a}} \cr {{f_b}} \cr {{f_c}} \cr } } \right] = k\left[ {\matrix{ 1 & 1 & 1 \cr {{\alpha ^2}} & \alpha & 1 \cr \alpha & {{\alpha ^2}} & 1 \cr } } \right]\left[ {\matrix{ {{f_p}} \cr {{f_n}} \cr {{f_o}} \cr } } \right]$$ where $$\,\alpha = {e^{j{{2\pi } \over 3}}}\,\,$$ and $$k$$ is a constant
Now, if it is given that:
$$\left[ {\matrix{ {{V_p}} \cr {{V_n}} \cr {{V_o}} \cr } } \right] = k\left[ {\matrix{ {0.5} & 0 & 0 \cr 0 & {0.5} & 0 \cr 0 & 0 & {2.0} \cr } } \right]\left[ {\matrix{ {{i_p}} \cr {{I_n}} \cr {{i_o}} \cr } } \right]\,\,$$ and $$\left[ {\matrix{ {{V_a}} \cr {{V_b}} \cr {{V_c}} \cr } } \right] = z\left[ {\matrix{ {{i_a}} \cr {{I_b}} \cr {{i_c}} \cr } } \right]\,\,$$ then,
A
$$z = \left[ {\matrix{ {1.0} & {0.5} & {0.75} \cr {0.75} & {1.0} & {0.5} \cr {0.5} & {0.75} & {1.0} \cr } } \right]$$
B
$$z = \left[ {\matrix{ {1.0} & {0.5} & {0.5} \cr {0.5} & {1.0} & {0.5} \cr {0.5} & {0.5} & {1.0} \cr } } \right]$$
C
$$z = 3{k^2}\left[ {\matrix{ {1.0} & {0.75} & {0.5} \cr {0.5} & {1.0} & {0.75} \cr {0.75} & {0.5} & {1.0} \cr } } \right]$$
D
$$z = {{{k^2}} \over 3}\left[ {\matrix{ {1.0} & { - 0.5} & { - 0.5} \cr { - 0.5} & {1.0} & { - 0.5} \cr { - 0.5} & { - 0.5} & {1.0} \cr } } \right]$$
2
GATE EE 2007
MCQ (Single Correct Answer)
+2
-0.6
Consider a synchronous generator connected to an infinite bus by two identical parallel transmission lines. The transient reactance $$x'$$ of the generator $$0.1$$ pu. Due to some previous disturbance, the rotor angle $$(d)$$ is undergoing an undamped oscillation, with the maximum value of $$\delta \left( t \right)$$ equal to $$\,{130^ \circ }\,.$$ One of the parallel lines trip due to relay mal-operation at an instant $$\,\,\,\,\,$$ when $$\,\delta \left( t \right)\,\, = {130^ \circ }\,\,$$ as shown in the figure. The maximum value of the per unit line reactance $$x,$$ such that the system does not lose synchronism subsequent to this tripping is GATE EE 2007 Power System Analysis - Power System Stability Question 19 English
A
0.87
B
0.74
C
0.67
D
0.54
3
GATE EE 2007
MCQ (Single Correct Answer)
+1
-0.3
The incremental cost curves in Rs/MWhr for two generators supplying a common load of $$700$$ MW are shown in the figures. The maximum and minimum generation limits are also indicated. The optimum generation schedule is: GATE EE 2007 Power System Analysis - Power Generation Cost Question 17 English
A
Generator A : $$400$$ MW,
Generator B : $$300$$ MW
B
Generator A : $$350$$ MW,
Generator B : $$350$$ MW
C
Generator A : $$450$$ MW,
Generator B : $$250$$ MW
D
Generator A : $$425$$ MW,
Generator B : $$275$$ MW
4
GATE EE 2007
MCQ (Single Correct Answer)
+1
-0.3
Consider a bundled conductor of an overhead line consisting of three identical sub-conductors placed at the corners of an equilateral triangle as shown in figure. If we neglect the charges on the other phase conductors and ground, and assume that spacing between sub-conductors is much larger than their radius, the maximum electric field intensity is experienced at GATE EE 2007 Power System Analysis - Parameters and Performance of Transmission Lines Question 5 English
A
Point $$X$$
B
Point $$Y$$
C
Point $$Z$$
D
Point $$W$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12