1
GATE CE 1991
Numerical
+1
-0
The length of a baseline measured on ground at an elevation of 300m above mean sea level is 2250 m. The required correction to reduce to sea level length. (given the radius of earth is 6370km) is _______.
Your input ____
2
GATE CE 1990
MCQ (Single Correct Answer)
+1
-0.3
The required slope correction for a length of 60m, along a gradient of 1 in 20 is
Questions Asked from Linear Measurements and Chain Survey (Marks 1)
Number in Brackets after Paper Indicates No. of Questions
GATE CE Subjects
Engineering Mechanics
Strength of Materials Or Solid Mechanics
Structural Analysis
Construction Material and Management
Reinforced Cement Concrete
Steel Structures
Geotechnical Engineering
Origin of Soils Definitions and Properties of Soils Classification of Soils and Clay Mineralogy Effective Stress and Permeability Seepage Analysis Compaction of Soil Compressibility and Consolidation Shear Strength of Soil Stress Distribution of Soil Retaining Wall and Earth Pressure Stability of Slopes Shallow Foundation Pile Foundation Soil Stabilization
Fluid Mechanics and Hydraulic Machines
Hydrology
Geomatics Engineering Or Surveying
Levelling Traversing Theodolites and Plane Table Surveying Measurement of Area, Volume and Theory of Errors and Survey Adjustment Field Astronomy and Photogrammetric Surveying Basics of GIS, GPS and Remote Sensing Angular Measurements and Compass Survey Basic Concepts Linear Measurements and Chain Survey
Environmental Engineering
Transportation Engineering
Engineering Mathematics
General Aptitude