1
GATE CE 2024 Set 2
MCQ (Single Correct Answer)
+1
-0.33

What is the CORRECT match between the survey instruments/parts of instruments shown in the table and the operations carried out with them?

Instruments/Parts of instrumentsOperations
P - Bubble tubei - Tacheometry
Q - Plumb bobii - Minor movements
R - Tangent screwiii - Centering
S - Stadia cross-wireiv - Levelling
A

P-ii, Q-iii, R-iv, S-i

B

P-iv, Q-iii, R-ii, S-i

C

P-i, Q-iii, R-ii, S-iv

D

P-iii, Q-iv, R-i, S-ii

2
GATE CE 2024 Set 2
MCQ (Single Correct Answer)
+1
-0.33

To finalize the direction of a survey, four surveyors set up a theodolite at a station P and performed all the temporary adjustments. From the station P, each of the surveyors observed the bearing to a tower located at station Q with the same instrument without shifting it. The bearings observed by the surveyors are 30° 30' 00", 30° 29' 40", 30° 30' 20" and 30° 31' 20". Assuming that each measurement is taken with equal precision, the most probable value of the bearing is

A

30° 29' 40"

B

30° 30' 20"

C

30° 30' 00"

D

30° 31' 20"

3
GATE CE 2024 Set 1
MCQ (Single Correct Answer)
+1
-0.33

If the number of sides resulting in a closed traverse is increased from three to four, the sum of the interior angles increases by

A

90°

B

180°

C

270°

D

360°

4
GATE CE 2024 Set 1
MCQ (Single Correct Answer)
+1
-0.33

A surveyor observes a zenith angle of 93° 00′ 00″ during a theodolite survey. The corresponding vertical angle is

A

− 03° 00′ 00″

B

+ 03° 00′ 00″

C

− 87° 00′ 00″

D

+ 87° 00′ 00″

GATE CE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12