1
GATE CE 2025 Set 1
Numerical
+1
-0

A water resources project with an expected life of 25 years has to be designed for an acceptable risk of $5 \%$ against a design flood. The return period for the design flood (in years) is __________ (rounded off to the nearest integer).

Your input ____
2
GATE CE 2022 Set 2
Numerical
+1
-0
A flood control structure having an expected life of n years is designed by considering a flood of return period T years. When T = n, and n $$\to$$ $$\infty$$, the structures hydrologic risk of failure in percentage is ____________. (rounded off to one decimal place)
Your input ____