A group of 9 friction piles are arranged in a square grid maintaining equal spacing in all directions. Each pile is of diameter 300 mm and length 7 m. Assume that the soil is cohesionless with effective friction angle 𝜙′ = 32°. What is the center-to-center spacing of the piles (in m) for the pile group efficiency of 60%?
A
0.582
B
0.486
C
0.391
D
0.677
2
GATE CE 2022 Set 1
Numerical
+1
-0

A square concrete pile of 10 m length is driven into a deep layer of uniform homogenous clay. Average unconfined compressive strength of the clay, determined through laboratory tests on undisturbed samples extracted from the clay layer, is 100 kPa. If the ultimate compressive load capacity of the driven pile is 632 kN, the required width of the pile is __________ mm. (in integer)

Bearing capacity factor Nc = 9; adhesion factor $$\alpha$$ = 0.7)

Your input ____
3
GATE CE 2022 Set 1
Numerical
+1
-0

A raft foundation of 30 m $$\times$$ 25 m is proposed to be constructed at a depth of 8 m in a sand layer. A 25 m thick saturated clay layer exists 2 m below the base of the raft foundation. Below the clay layer, a dense sand layer exists at the site. A 25 mm thick undisturbed sample was collected from the mid-depth of the clay layer and tested in a laboratory oedometer under double drainage condition. It was found that the soil sample had undergone 50% consolidation settlement in 10 minutes. The time (in days) required for 25% consolidation settlement of the raft foundation will be ___________. (round off to the nearest integer)

Your input ____
GATE CE Subjects
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12