1
GATE EE 2015 Set 2
Numerical
+2
-0
The incremental costs (in rupees/$$MWh$$) of operating two generating units are functions of their respective powers $${P_1}$$ and $${P_2}$$ in $$MW,$$ and are given by $$${{d{C_1}} \over {d{P_1}}} = 0.2{P_1} + 50$$$ $$${{d{C_2}} \over {d{P_2}}} = 0.24{P_2} + 40$$$
Where, $$$\eqalign{ & 20\,MW \le {P_1} \le 150\,MW \cr & 20\,MW \le {P_2} \le 150MW. \cr} $$$
For a certain load demand, $${P_1}$$ and $${P_2}$$ have been chosen such that $$\,\,d{C_1}/d{P_1} = 76\,Rs/MWh\,\,$$ and $$\,d{C_2}/d{P_2} = 68.8\,Rs/MWh.\,\,$$ If the generations are rescheduled to minimize the total cost, then $${P_2}$$ is ____________.
Your input ____
2
GATE EE 2015 Set 2
MCQ (Single Correct Answer)
+2
-0.6
A $$3$$-phase transformer rated for $$33 kV/11kV$$ is connected in delta/star as shown in figure. The current transformers $$\left( {C{T_s}} \right)$$ on low and high voltage sides have a ratio of $$500/5.$$ Find the currents $${i_1}$$ and $${i_2}$$, if the fault current is $$300$$ $$A$$ as shown in figure. GATE EE 2015 Set 2 Power System Analysis - Switch Gear and Protection Question 6 English
A
$${i_1} = {1 \over {\sqrt 3 }}A,\,\,{i_2} = 0\,A$$
B
$${i_1} = 0\,A,\,\,{i_2} = 0\,A$$
C
$${i_1} = 0\,A,\,\,{i_2} = {1 \over {\sqrt 3 }}A$$
D
$${i_1} = {1 \over {\sqrt 3 }}A,\,\,{i_2} = {1 \over {\sqrt 3 }}A$$
3
GATE EE 2015 Set 2
MCQ (Single Correct Answer)
+1
-0.3
A $$3$$-bus power system network consists of $$3$$ transmission lines. The bus admittance matrix of the uncompensated system is
$$\left[ {\matrix{ { - j6} & {j3} & {j4} \cr {j3} & { - j7} & {j5} \cr {j4} & {j5} & { - j8} \cr } } \right]\,pu$$
If the shunt capacitance of all transmission lines is $$50$$% compensated, the imaginary part of the $$3$$rd row $$3$$rd column element (in $$pu$$) of the bus admittance matrix after compensation is
A
$$-j7.0$$
B
$$-j8.5$$
C
$$-j7.5$$
D
$$-j9.0$$
4
GATE EE 2015 Set 2
MCQ (Single Correct Answer)
+2
-0.6
The synchronous generator shown in the figure is supplying active power to an infinite bus via two short, lossless transmission lines, and is initially in steady state. The mechanical power input to the generator and the voltage magnitude E are constant. If one line is tripped at time t1 by opening the circuit breakers at the two ends (although there is no fault), then it is seen that the generator undergoes a stable transient. Which one of the following waveforms of the rotor angle $$\delta $$ shows the transient correctly? GATE EE 2015 Set 2 Power System Analysis - Power System Stability Question 13 English
A
GATE EE 2015 Set 2 Power System Analysis - Power System Stability Question 13 English Option 1
B
GATE EE 2015 Set 2 Power System Analysis - Power System Stability Question 13 English Option 2
C
GATE EE 2015 Set 2 Power System Analysis - Power System Stability Question 13 English Option 3
D
GATE EE 2015 Set 2 Power System Analysis - Power System Stability Question 13 English Option 4
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12