1
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
The Gauss Seidel load flow method has following disadvantages. Tick the incorrect student.
A
Unreliable convergence
B
Slow convergence
C
Choice of slack bus effects convergence
D
A good initial guess for voltages is essential for convergence
2
GATE EE 2006
MCQ (Single Correct Answer)
+1
-0.3
In a biased differential relay the bias is defined as a ratio of
A
Number of turns of restraining and operating coil
B
Operating coil current and restraining coil current
C
Fault current and operating coil current
D
Fault current and restraining coil current
3
GATE EE 2006
MCQ (Single Correct Answer)
+1
-0.3
Keeping in view the cost and overall effectiveness, the following circuit breaker is best suited for capacitor bank switching
A
vacuum
B
air blast
C
SF6
D
oil
4
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
A generator feeds power to an infinite bus through a double circuit transmission line. A $$3$$ phase fault occurs at the middle point of one of the lines. The infinite bus voltage is $$1$$ pu, the transient internal voltage of the generator is $$1.1$$ pu and the equivalent transfer admittance during fault is $$0.8$$ pu. The 100 MVA generator has an inertia constant of $$5$$ MJ/MVA and it was delivering $$1.0$$ pu power prior of the fault with rotor power angle of $${30^ \circ }\,\,$$. The system frequency is 50Hz.

If the initial accelerating power is $$X$$ pu, the initial acceleration in elect deg/sec2, and the inertia constant in MJ-sec/elect deg respectively will be

A
$$31.4$$$$X,$$ $$18$$
B
$$1800$$ $$X,$$ $$0.056$$
C
$$X/1800,$$ $$0.056$$
D
$$X/31.4,$$ $$18$$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12