1
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
The Gauss Seidel load flow method has following disadvantages. Tick the incorrect student.
A
Unreliable convergence
B
Slow convergence
C
Choice of slack bus effects convergence
D
A good initial guess for voltages is essential for convergence
2
GATE EE 2006
MCQ (Single Correct Answer)
+1
-0.3
In a biased differential relay the bias is defined as a ratio of
A
Number of turns of restraining and operating coil
B
Operating coil current and restraining coil current
C
Fault current and operating coil current
D
Fault current and restraining coil current
3
GATE EE 2006
MCQ (Single Correct Answer)
+1
-0.3
Keeping in view the cost and overall effectiveness, the following circuit breaker is best suited for capacitor bank switching
A
vacuum
B
air blast
C
SF6
D
oil
4
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
A generator feeds power to an infinite bus through a double circuit transmission line. A 3 phase fault occurs at the middle point of one of the lines. The infinite bus voltage is 1 pu, the transient internal voltage of the generator is 1.1 pu and the equivalent transfer admittance during fault is 0.8 pu. The 100 MVA generator has an inertia constant of $$5$$ MJ/MVA and it was delivering 1.0 pu power prior of the fault with rotor power angle of $${30^ \circ }\,\,$$. The system frequency is 50Hz.

The initial accelerating power (in pu) will be

A
1.0
B
0.6
C
0.56
D
0.4
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12