1
GATE EE 2006
MCQ (Single Correct Answer)
+1
-0.3
Keeping in view the cost and overall effectiveness, the following circuit breaker is best suited for capacitor bank switching
A
vacuum
B
air blast
C
SF6
D
oil
2
GATE EE 2006
MCQ (Single Correct Answer)
+1
-0.3
In a biased differential relay the bias is defined as a ratio of
A
Number of turns of restraining and operating coil
B
Operating coil current and restraining coil current
C
Fault current and operating coil current
D
Fault current and restraining coil current
3
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
The Gauss Seidel load flow method has following disadvantages. Tick the incorrect student.
A
Unreliable convergence
B
Slow convergence
C
Choice of slack bus effects convergence
D
A good initial guess for voltages is essential for convergence
4
GATE EE 2006
MCQ (Single Correct Answer)
+2
-0.6
For a power system the admittance and impedance matrices for the fault studies are as follows. $$$\eqalign{ & {Y_{bus}} = \left[ {\matrix{ { - j8.75} & {j1.25} & {j2.50} \cr {j1.25} & { - j6.25} & {j2.50} \cr {j2.50} & {j2.50} & { - j5.00} \cr } } \right] \cr & {Z_{bus}} = \left[ {\matrix{ {j0.16} & {j0.08} & {j0.12} \cr {j0.08} & {j0.24} & {j0.16} \cr {j0.12} & {j0.16} & {j0.34} \cr } } \right] \cr} $$$

The pre-fault voltages are $$1.0$$ $$p.u.$$ at all the buses. The system was unloaded prior to the fault. A solid $$3$$ phase fault takes place at bus $$2.$$

The post fault voltages at buses $$1$$ and $$3$$ in per unit respectively are

A
$$0.24,0.63$$
B
$$0.31, 0.76$$
C
$$0.33, 0.67$$
D
$$0.67, 0.33$$