1
GATE ME 2012
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following is NOT a decision taken during the aggregate production planning stage?
A
Scheduling of machines
B
Amount of labour to be committed
C
Rate at which production should happen
D
Inventory to be carried forward
2
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
A solid circular shaft needs to be designed to transmit a torque of $$50$$ $$N.m.$$ If the allowable shear stress of the material is $$140$$ $$MPa,$$ assuming a factor of safety of $$2,$$ the minimum allowable design diameter in $$mm$$ is
A
$$8$$
B
$$16$$
C
$$24$$
D
$$32$$
3
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
The homogeneous state of stress for a metal part undergoing plastic deformation is $$$T = \left( {\matrix{ {10} & 5 & 0 \cr 5 & {20} & 0 \cr 0 & 0 & { - 10} \cr } } \right)$$$

Where the stress component values are in $$MPa.$$ Using von Mises yield criterion, the value of estimated shear yield stress, in $$MPa$$ is

A
$$9.50$$
B
$$16.07$$
C
$$28.52$$
D
$$49.41$$
4
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
A force of $$400$$ $$N$$ is applied to the brake drum of $$0.5$$ $$m$$ diameter in a band-brake system as shown in the figure, where the wrapping angle is $${180^ \circ }$$ . If the coefficient of friction between the drum and the band is $$0.25,$$ the braking torque applied, in $$N.m$$ is GATE ME 2012 Machine Design - Design of Brakes and Clutches Question 15 English
A
$$100.6$$
B
$$54.4$$
C
$$22.1$$
D
$$15.7$$