Water $$\left( {{C_p} = 4.18\,kJ/kg.K} \right)$$ at $${80^ \circ }C$$ enters a counter flow heat exchanger with a mass flow rate of $$0.5kg/s.$$ Air $$\left( {{C_p} = 1\,kJ/kg.\,K} \right)$$ enters at $${80^ \circ }C$$ with a mass flow rate $$2.09$$ $$kg/s.$$ If the effectiveness of the heat exchanger is $$0.8,$$ the $$LMTD$$ (in $$^ \circ C$$) is
A
$$40$$
B
$$20$$
C
$$10$$
D
$$5$$
2
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below. GATE ME 2012 Industrial Engineering - Pert and Cpm Question 14 English

The critical path for the project is

A
$$a-b-e-g-h$$
B
$$a-c-g-h$$
C
$$a-d-f-h$$
D
$$a-b-c-f-h$$
3
GATE ME 2012
MCQ (Single Correct Answer)
+2
-0.6
For a particular project, eight activities are to be carried out. Their relationships with other activities and expected durations are mentioned in the table below. GATE ME 2012 Industrial Engineering - Pert and Cpm Question 13 English

If the duration of activity $$''f ''$$ alone is changed from $$9$$ to $$10$$ days, then the

A
critical path remains the same and the total duration to complete the project changes to $$19$$ days.
B
critical path and the total duration to complete the project remains the same.
C
critical path changes but the total duration to complete the project remains the same.
D
critical path changes and the total duration to complete the project changes to $$17$$ days.
4
GATE ME 2012
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following is NOT a decision taken during the aggregate production planning stage?
A
Scheduling of machines
B
Amount of labour to be committed
C
Rate at which production should happen
D
Inventory to be carried forward
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12