1
GATE ME 2022 Set 2
Numerical
+1
-0
An electric car manufacturer underestimated the January sales of car by 20 units, while the actual sales was 120 units. If the manufacturer uses exponential smoothing method with a smoothing constant of α = 0.2, then the sales forecast for the month of February of the same year is ______ units (in integer). 
Your input ____
2
GATE ME 2022 Set 2
Numerical
+1
-0
The demand of a certain part is 1000 parts/year and its cost is Rs. 1000/part. The orders are placed based on the economic order quantity (EOQ). The cost of ordering is Rs. 100/order and the lead time for receiving the orders is 5 days. If the holding cost is Rs. 20/part/year, the inventory level for placing the orders is _______ parts (round off to the nearest integer).
Your input ____
3
GATE ME 2022 Set 2
MCQ (Single Correct Answer)
+2
-0.66

Parts P1 - P7 are machined first on a milling machine and then polished at a separate machine. Using the information in the following table, the minimum total completion time required for carrying out both the operations for all 7 parts is _______ hours.

Part

Milling (hours)

Polishing (hours)

P1

8

6

P2

3

2

P3

3

4

P4

4

6

P5

5

7

P6

6

4

P7

2

1

A
31
B
33
C
30
D
32
4
GATE ME 2022 Set 2
Numerical
+2
-0

A project consists of five activities (A, B, C, D and E). The duration of each activity follows beta distribution. The three time estimates (in weeks) of each activity and immediate predecessor(s) are listed in the table. The expected time of the project completion is ______ weeks (in integer).

Activity

Time estimates (in weeks)

Immediate predecessor(s)

Optimistic time

Most likely time

Pessimistic time

A

4

5

6

None

B

1

3

5

A

C

1

2

3

A

D

2

4

6

C

E

3

4

5

B, D

Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12