1
GATE ME 2009
MCQ (Single Correct Answer)
+1
-0.3
The expected time $$\left( {{t_e}} \right)$$ of a $$PERT$$ activity in terms of optimistic time $$\left( {{t_0}} \right)$$, pessimistic $$\left( {{t_p}} \right)$$ and most likely time $$\left( {{t_L}} \right)$$ is given by
A
$${t_e} = {{{t_0} + 4{t_L} + {t_P}} \over 6}$$
B
$${t_e} = {{{t_0} + 4{t_P} + {t_L}} \over 6}$$
C
$${t_e} = {{{t_0} + 4{t_L} + {t_P}} \over 3}$$
D
$${t_e} = {{{t_0} + 4{t_P} + {t_L}} \over 3}$$
2
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network GATE ME 2009 Industrial Engineering - Pert and Cpm Question 20 English 1

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :

GATE ME 2009 Industrial Engineering - Pert and Cpm Question 20 English 2

The critical path duration of the network (in days) is

A
$$11$$
B
$$14$$
C
$$17$$
D
$$18$$
3
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network GATE ME 2009 Industrial Engineering - Pert and Cpm Question 19 English 1

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :

GATE ME 2009 Industrial Engineering - Pert and Cpm Question 19 English 2

The standard deviation of the critical path is

A
$$0.33$$
B
$$0.55$$
C
$$0.77$$
D
$$1.66$$
4
GATE ME 2009
MCQ (Single Correct Answer)
+1
-0.3
Which of the following forecasting methods takes a fraction of forecast error into account for the next period forecast?
A
simple average method
B
moving average method
C
weighted moving average method
D
exponential smoothing method
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12