The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :
The standard deviation of the critical path is
Maximize: $$Z = 3{x_1} + 2{x_2}$$
$$\,\,$$ Subject $$\,\,$$ to
$$\eqalign{
& \,\,\,\,\,\,\,{x_1} \le 4 \cr
& \,\,\,\,\,\,\,{x_2} \le 6 \cr
& 3{x_1} + 2{x_2} \le 18 \cr
& {x_1} \ge 0,\,\,{x_2} \ge 0 \cr} $$
Average flow time (in days) for the above jobs using Shortest Processing Time rule is
Given that the tooth geometry factor is $$0.32$$ and the combined effect of dynamic load and allied factors intensifying the stress is $$1.5;$$ the minimum allowable stress (in $$MPa$$) for the gear material is