1
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
A company uses $$2555$$ units of an item annually. Delivery lead time is $$8$$ days. The recorder point (in number of units) to achieve optimum inventory is
A
$$7$$
B
$$8$$
C
$$56$$
D
$$60$$
2
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following network GATE ME 2009 Industrial Engineering - Pert and Cpm Question 20 English 1

The optimistic time, most likely time and pessimistic time of all the activities are given in the table below :

GATE ME 2009 Industrial Engineering - Pert and Cpm Question 20 English 2

The standard deviation of the critical path is

A
$$0.33$$
B
$$0.55$$
C
$$0.77$$
D
$$1.66$$
3
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Consider the following Linear Programming problem $$(LLP)$$

Maximize: $$Z = 3{x_1} + 2{x_2}$$
$$\,\,$$ Subject $$\,\,$$ to
$$\eqalign{ & \,\,\,\,\,\,\,{x_1} \le 4 \cr & \,\,\,\,\,\,\,{x_2} \le 6 \cr & 3{x_1} + 2{x_2} \le 18 \cr & {x_1} \ge 0,\,\,{x_2} \ge 0 \cr} $$

A
The $$LPP$$ has a unique optimal solution.
B
The $$LPP$$ is infeasible
C
The $$LPP$$ is unbounded
D
The $$LPP$$ has multiple optimal solutions.
4
GATE ME 2009
MCQ (Single Correct Answer)
+2
-0.6
Six jobs arrived in a sequence as given below: GATE ME 2009 Industrial Engineering - Scheduling Question 9 English

Average flow time (in days) for the above jobs using Shortest Processing Time rule is

A
$$20.83$$
B
$$23.16$$
C
$$125.00$$
D
$$139.00$$