1
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A set of $$5$$ jobs is to be processed on a single machine. The processing time (in days) is given in the table below. The holding cost for each job is Rs. $$K$$ per day. GATE ME 2008 Industrial Engineering - Scheduling Question 8 English

A schedule that minimizes the total inventory cost is

A
$$T - S - Q - R - P$$
B
$$P - R - S - Q - T$$
C
$$T - R - S - Q - P$$
D
$$P - Q - R - S - T$$
2
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A steel bar of $$10$$ $$mm\,\, \times \,\,50\,\,mm$$ is cantilevered with two $$M12$$ bolts ($$P$$ and $$Q$$) to support a static load of $$4$$ $$kN$$ as shown in figure aside. GATE ME 2008 Machine Design - Bolted Riveted and Welded Joints Question 2 English

The primary and secondary shear loads on rivet $$p,$$ respectively are

A
$$2\,\,kN,\,\,20\,\,kN$$
B
$$20$$ $$kN,$$ $$2kN$$
C
$$20$$ $$kN,$$ $$0$$ $$kN$$
D
$$0$$ $$kN$$, $$20$$ $$kN$$
3
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A steel bar of $$10$$ $$mm\,\, \times \,\,50\,\,mm$$ is cantilevered with two $$M12$$ bolts ($$P$$ and $$Q$$) to support a static load of $$4$$ $$kN$$ as shown in figure aside. GATE ME 2008 Machine Design - Bolted Riveted and Welded Joints Question 1 English

The resultant shear stress on rivet $$P$$ is closest to

A
$$132$$ $$MPa$$
B
$$159$$ $$MPa$$
C
$$178$$ $$MPa$$
D
$$195$$ $$MPa$$
4
GATE ME 2008
MCQ (Single Correct Answer)
+2
-0.6
A spur gate has a module of $$3mm,$$ number of teeth $$16,$$ a face width of $$36mm$$ and a pressure angle of $${20^ \circ }$$. It is transmitting a power of $$3KW$$ at $$20rev/s.$$ Taking a velocity factor of $$1.5$$ and a form factor of $$0.3,$$ the stress in the gear tooth is about
A
$$32MPa$$
B
$$46MPa$$
C
$$58MPa$$
D
$$70MPa$$
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12