A project consists of activities $$A$$ to $$M$$ shown in the net in the following figure with the duration of the activities marked in days.

The project can be completed

A
between $$18,$$ $$19$$ day
B
between $$20, 22$$ days
C
between $$24, 26$$ days
D
between $$60, 70$$ days
2
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
The sale of cycles in a shop in four consecutive months are given as $$70, 68, 82 95.$$ Exponentially smoothing average method with a smoothing factor of $$0.4$$ is used in forecasting. The expected number of sales in the next month is
A
$$59$$
B
$$72$$
C
$$86$$
D
$$136$$
3
GATE ME 2003
MCQ (Single Correct Answer)
+2
-0.6
A manufacturer produces two types of products, $$1$$ and $$2,$$ at production levels of $${x_1}$$ and $${x_2}$$ respectively. The profit is given is$$2{x_1} + 5{x_2}.$$ The production constraints are $$$\eqalign{ & {x_1} + 3{x_2} \le 40 \cr & 3{x_1} + {x_2} \le 24 \cr & {x_1} + {x_2} \le 10 \cr & {x_1} > 0,\,{x_2} > 0 \cr} $$$

The maximum profit which can meet the constraints is

A
$$29$$
B
$$38$$
C
$$44$$
D
$$75$$
4
GATE ME 2003
MCQ (Single Correct Answer)
+1
-0.3
In terms of theoretical stress concentration factor $$\left( {{k_t}} \right)$$ and fatigue stress concentration factor $$\left( {{k_f}} \right),$$ the notch sensitivity $$'q'$$ is expressed as
A
$$\left( {{k_f} - 1} \right)/\left( {{k_t} - 1} \right)$$
B
$$\left( {{k_f} - 1} \right)/\left( {{k_t} + 1} \right)$$
C
$$\left( {{k_t} - 1} \right)/\left( {{k_f} - 1} \right)$$
D
$$\left( {{k_f} + 1} \right)/\left( {{k_f} + 1} \right)$$