1
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
A dummy activity is used in $$PERT$$ network to describe
A
Precedence relationship
B
Necessary time delay
C
Resource restriction
D
Resource idleness
2
GATE ME 1997
Subjective
+5
-0
Determine the number of production runs and also the total incremental cost in a factory for the data given below: GATE ME 1997 Industrial Engineering - Inventory Control Question 3 English
3
GATE ME 1997
Subjective
+5
-0
A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 3 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

4
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
The most commonly used criteria for measuring forecast error is
A
Mean absolute deviation
B
Mean absolute percentage error
C
Mean standard error
D
Mean square error
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12