1
GATE ME 1997
Subjective
+5
-0
Determine the number of production runs and also the total incremental cost in a factory for the data given below: GATE ME 1997 Industrial Engineering - Inventory Control Question 8 English
2
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
The most commonly used criteria for measuring forecast error is
A
Mean absolute deviation
B
Mean absolute percentage error
C
Mean standard error
D
Mean square error
3
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
A dummy activity is used in $$PERT$$ network to describe
A
Precedence relationship
B
Necessary time delay
C
Resource restriction
D
Resource idleness
4
GATE ME 1997
Subjective
+5
-0
People arrive at a hotel in a Poisson distributed arrival rate of $$8$$ per hour. Service time distribution is closely approximated by the negative exponential. The average service time is $$5$$ minutes. Calculate (a) the mean number in the waiting line; (b) the mean number in the system; (c) the waiting time in the queue; (d) the mean time in the system, and (e) the utilization factor.