1
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
Setup costs do not include
A
Labour cost of setting up machines
B
Ordering cost of raw material
C
Maintenance cost of the machines
D
Cost of processing the work piece
2
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
A dummy activity is used in $$PERT$$ network to describe
A
Precedence relationship
B
Necessary time delay
C
Resource restriction
D
Resource idleness
3
GATE ME 1997
Subjective
+5
-0
Determine the number of production runs and also the total incremental cost in a factory for the data given below: GATE ME 1997 Industrial Engineering - Inventory Control Question 8 English
4
GATE ME 1997
Subjective
+5
-0
A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 6 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

EXAM MAP