1
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
Setup costs do not include
A
Labour cost of setting up machines
B
Ordering cost of raw material
C
Maintenance cost of the machines
D
Cost of processing the work piece
2
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
A dummy activity is used in $$PERT$$ network to describe
A
Precedence relationship
B
Necessary time delay
C
Resource restriction
D
Resource idleness
3
GATE ME 1997
Subjective
+5
-0
Determine the number of production runs and also the total incremental cost in a factory for the data given below: GATE ME 1997 Industrial Engineering - Inventory Control Question 7 English
4
GATE ME 1997
Subjective
+5
-0
A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 5 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12