1
GATE ME 1997
Subjective
+5
-0
A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 5 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

2
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
The most commonly used criteria for measuring forecast error is
A
Mean absolute deviation
B
Mean absolute percentage error
C
Mean standard error
D
Mean square error
3
GATE ME 1997
MCQ (Single Correct Answer)
+2
-0.6
In a forecasting model, at the end of period $$13,$$ the forecasted value for period $$14$$ is $$75.$$ Actual value in the periods $$14$$ to $$16$$ are constant at $$100$$. if the assumed simple exponential smoothing parameter is $$0.5,$$ then the $$MSE$$ at the end of period $$16$$ is
A
$$820.31$$
B
$$273.44$$
C
$$43.75$$
D
$$14.58$$
4
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
The cost of providing service in a queuing system increases with
A
Increased mean time in the queue
B
Increased arrival rate
C
Decreased mean time in the queue
D
Decreased arrival rate
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12