A project plan is given below: GATE ME 1997 Industrial Engineering - Pert and Cpm Question 3 English

(a) Construct a $$PERT$$ network
(b) Find the critical path and estimate the project duration.

2
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
The most commonly used criteria for measuring forecast error is
A
Mean absolute deviation
B
Mean absolute percentage error
C
Mean standard error
D
Mean square error
3
GATE ME 1997
MCQ (Single Correct Answer)
+2
-0.6
In a forecasting model, at the end of period $$13,$$ the forecasted value for period $$14$$ is $$75.$$ Actual value in the periods $$14$$ to $$16$$ are constant at $$100$$. if the assumed simple exponential smoothing parameter is $$0.5,$$ then the $$MSE$$ at the end of period $$16$$ is
A
$$820.31$$
B
$$273.44$$
C
$$43.75$$
D
$$14.58$$
4
GATE ME 1997
MCQ (Single Correct Answer)
+1
-0.3
The cost of providing service in a queuing system increases with
A
Increased mean time in the queue
B
Increased arrival rate
C
Decreased mean time in the queue
D
Decreased arrival rate
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12