1
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Little’s law is relationship between
A
stock level and lead time in an inventory system
B
waiting time and length of the queue in a queuing system
C
number of machines and job due dates in a scheduling problem
D
uncertainty in the activity time and project completion time
2
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Simplex method of solving linear programming problem uses
A
all the points in the feasible region
B
only the corner points of the feasible region
C
intermediate points within the infeasible region
D
only the interior points in the feasible region.
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 6 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 5 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

A
$$0$$
B
$$2$$
C
$$6$$
D
$$8$$
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12