1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Annual demand for window frames is $$10000.$$ Each frame costs Rs. $$200$$ and ordering cost is Rs. $$300$$ per order. Inventory holding cost is Rs. $$40$$ per frame per year. The supplier is willing to offer $$2\% $$ discount if the order quantity is $$1000$$ or more, and $$4\% $$ if order quantity is $$2000$$ or more. If the total cost is to be minimized, the retailer should
A
order $$200$$ frames every time
B
accept $$2\% $$ discount
C
accept $$4\% $$ discount
D
order Economic Order Quantity
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The project activities, precedence relationships and durations are described in the table. The critical path of the project is GATE ME 2010 Industrial Engineering - Pert and Cpm Question 19 English
A
$$P-R-T-V$$
B
$$Q-S-T-V$$
C
$$P-R-U-W$$
D
$$Q-S-U-W$$
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The demand and forecast for February are $$12000$$ and $$10275,$$ respectively. Using single exponential smoothening method (smoothening coefficient $$= 0.25$$), forecast for the month of March is
A
$$431$$
B
$$9587$$
C
$$10706$$
D
$$11000$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Little’s law is relationship between
A
stock level and lead time in an inventory system
B
waiting time and length of the queue in a queuing system
C
number of machines and job due dates in a scheduling problem
D
uncertainty in the activity time and project completion time