GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Annual demand for window frames is $$10000.$$ Each frame costs Rs. $$200$$ and ordering cost is Rs. $$300$$ per order. Inventory holding cost is Rs. $$40$$ per frame per year. The supplier is willing to offer $$2\% $$ discount if the order quantity is $$1000$$ or more, and $$4\% $$ if order quantity is $$2000$$ or more. If the total cost is to be minimized, the retailer should
A
order $$200$$ frames every time
B
accept $$2\% $$ discount
C
accept $$4\% $$ discount
D
order Economic Order Quantity
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The demand and forecast for February are $$12000$$ and $$10275,$$ respectively. Using single exponential smoothening method (smoothening coefficient $$= 0.25$$), forecast for the month of March is
A
$$431$$
B
$$9587$$
C
$$10706$$
D
$$11000$$
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 8 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 7 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

A
$$0$$
B
$$2$$
C
$$6$$
D
$$8$$