1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Annual demand for window frames is $$10000.$$ Each frame costs Rs. $$200$$ and ordering cost is Rs. $$300$$ per order. Inventory holding cost is Rs. $$40$$ per frame per year. The supplier is willing to offer $$2\% $$ discount if the order quantity is $$1000$$ or more, and $$4\% $$ if order quantity is $$2000$$ or more. If the total cost is to be minimized, the retailer should
A
order $$200$$ frames every time
B
accept $$2\% $$ discount
C
accept $$4\% $$ discount
D
order Economic Order Quantity
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The project activities, precedence relationships and durations are described in the table. The critical path of the project is GATE ME 2010 Industrial Engineering - Pert and Cpm Question 18 English
A
$$P-R-T-V$$
B
$$Q-S-T-V$$
C
$$P-R-U-W$$
D
$$Q-S-U-W$$
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The demand and forecast for February are $$12000$$ and $$10275,$$ respectively. Using single exponential smoothening method (smoothening coefficient $$= 0.25$$), forecast for the month of March is
A
$$431$$
B
$$9587$$
C
$$10706$$
D
$$11000$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Little’s law is relationship between
A
stock level and lead time in an inventory system
B
waiting time and length of the queue in a queuing system
C
number of machines and job due dates in a scheduling problem
D
uncertainty in the activity time and project completion time
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12