1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 8 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 7 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

A
$$0$$
B
$$2$$
C
$$6$$
D
$$8$$
3
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Simplex method of solving linear programming problem uses
A
all the points in the feasible region
B
only the corner points of the feasible region
C
intermediate points within the infeasible region
D
only the interior points in the feasible region.
4
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Tooth interference in an external involute spur gear pair can be reduced by
A
decreasing center distance between gears
B
decreasing module
C
decreasing pressure angle
D
increasing number of teeth