1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 6 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 5 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

A
$$0$$
B
$$2$$
C
$$6$$
D
$$8$$
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
A bracket shown in fig. is rigidly mounted on wall using four rivets. Each rivet is $$6mm$$ in diameter and has an effective length of $$12mm.$$ GATE ME 2010 Machine Design - Bolted Riveted and Welded Joints Question 13 English

Direct shear stress in $$MPa$$ in the most heavily loaded rivet is

A
$$4.4$$
B
$$8.8$$
C
$$17.6$$
D
$$35.2$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Tooth interference in an external involute spur gear pair can be reduced by
A
decreasing center distance between gears
B
decreasing module
C
decreasing pressure angle
D
increasing number of teeth
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12