1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 8 English

If the Earliest Due Date $$(EDD)$$ rule is used to sequence the jobs, the number of jobs delayed is

A
$$1$$
B
$$2$$
C
$$3$$
D
$$4$$
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Four jobs are to be processed on a machine as per data listed in the table. GATE ME 2010 Industrial Engineering - Scheduling Question 7 English

Using the Shortest Processing Time $$(SPT)$$ rule, total tardiness is

A
$$0$$
B
$$2$$
C
$$6$$
D
$$8$$
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
A bracket shown in fig. is rigidly mounted on wall using four rivets. Each rivet is $$6mm$$ in diameter and has an effective length of $$12mm.$$ GATE ME 2010 Machine Design - Bolted Riveted and Welded Joints Question 15 English

Direct shear stress in $$MPa$$ in the most heavily loaded rivet is

A
$$4.4$$
B
$$8.8$$
C
$$17.6$$
D
$$35.2$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Tooth interference in an external involute spur gear pair can be reduced by
A
decreasing center distance between gears
B
decreasing module
C
decreasing pressure angle
D
increasing number of teeth
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12