1
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
Match the following

List-$${\rm I}$$
$$P.$$ Compressible flow
$$Q.$$ Free surface flow
$$R.$$ Boundary layer flow
$$S.$$ Pipe flow
$$T.$$ Heat convection

List-$${\rm II}$$
$$U.$$ Renolds number
$$V.$$ Nussult number
$$W.$$ Weber number
$$X.$$ Froude number
$$Y.$$ Mach number
$$Z.$$ Skin friction coefficient

A
$$P - U,\,\,Q - X,\,\,R - V,\,\,S - Z,\,\,T - W$$
B
$$P - W,\,\,Q - X,\,\,R - Z,\,\,S - U,\,\,T - V$$
C
$$P - Y,\,\,Q - W,\,\,R - Z,\,\,S - U,\,\,T - X$$
D
$$P - Y,\,\,Q - W,\,\,R - Z,\,\,S - U,\,\,T - V$$
2
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
A fin has $$5mm$$ diameter and $$100mm$$ length. The thermal conductivity of fin material is $$400W/m K.$$ One end of the fin is maintained at $${130^ \circ }C$$ and its remaining surface is exposed to ambient air at $${30^ \circ }C.$$ if the convective heat transfer coefficient is $$40W/{m^2}K,$$ the heat loss (in $$W$$) from the fin is
A
$$0.08$$
B
$$5.0$$
C
$$7.0$$
D
$$7.8$$
3
GATE ME 2010
MCQ (Single Correct Answer)
+2
-0.6
The project activities, precedence relationships and durations are described in the table. The critical path of the project is GATE ME 2010 Industrial Engineering - Pert and Cpm Question 19 English
A
$$P-R-T-V$$
B
$$Q-S-T-V$$
C
$$P-R-U-W$$
D
$$Q-S-U-W$$
4
GATE ME 2010
MCQ (Single Correct Answer)
+1
-0.3
Little’s law is relationship between
A
stock level and lead time in an inventory system
B
waiting time and length of the queue in a queuing system
C
number of machines and job due dates in a scheduling problem
D
uncertainty in the activity time and project completion time