1
GATE ME 2004
MCQ (Single Correct Answer)
+5
-1.5
A standard machine tool and an automatic machine tool are being compared for the production of a component. Following data refers to the two machines. GATE ME 2004 Production Engineering - Metal Cutting Question 1 English

The breakeven production batch size above which the automatic machine tool will be economical to use, will be

A
$$4$$
B
$$5$$
C
$$24$$
D
$$225$$
2
GATE ME 2004
MCQ (Single Correct Answer)
+5
-1.5
In an orthogonal cutting test on mild steel, the following data were obtained
Cutting speed: $$40$$ $$m/min,$$
Depth of cut: $$0.3$$ $$mm,$$
Tool rake angle : $$ + {5^ \circ },$$
Chip thickness: $$1.5$$ $$mm,$$
Cutting force: $$900$$ $$N,$$
Thrust force: $$450$$ $$N$$
Using Merchant's analysis, the Friction angle during the machining will be
A
$${26.5^ \circ }$$
B
$${31.5^ \circ }$$
C
$${45^ \circ }$$
D
$${63.40^ \circ }$$
3
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
Through holes of $$10$$ $$mm$$ diameter are to be drilled in steel plate of $$20$$ $$mm$$ thickness. Drill spindle speed is $$300$$ $$rpm,$$ feed $$0.2$$ $$mm/rev$$ and drill point angle is $${120^0}.$$ Assuming drill over travel of $$2mm$$ the time for producing a hole will be
A
$$4$$ seconds
B
$$25$$ seconds
C
$$100$$ seconds
D
$$110$$ seconds
4
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
$$10$$ $$mm$$ diameter holes are to be punched in a steel sheet of $$3$$ $$mm$$ thickness. Shear strength of the material is $$400\,\,N/m{m^2}$$ and penetration is $$40\% $$. Shear provided on the punch is $$2$$ $$mm.$$ The blanking force during the operation will be
A
$$22.6$$ $$kN$$
B
$$37.7$$ $$kN$$
C
$$61.6$$ $$kN$$
D
$$94.3$$ $$kN$$