1
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
A maintenance service facility has Poisson arrival rates, negative exponential service time and operates on a ‘first come first served’ queue discipline. Breakdowns occur on an average of $$3$$ per day with a range of zero to eight. The maintenance crew can service an average of $$6$$ machines per day with a range of zero to seven. The mean waiting time for an item to be serviced would be
A
$${1 \over 6}$$ day
B
$${1 \over 3}$$ day
C
$$1$$ day
D
$$3$$ day
2
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
An electronic equipment manufacturer has decided to add a component sub-assembly operation that can produce $$80$$ units during a regular $$8$$-hour shift. This operation consists of three activities as below . GATE ME 2004 Industrial Engineering - Line Balancing Question 2 English

For line balancing the number of work stations required for the activities $$M, E$$ and $$T$$ would respectively be

A
$$2, 3, 1$$
B
$$3, 2, 1$$
C
$$2, 4, 2$$
D
$$2, 1, 3$$
3
GATE ME 2004
MCQ (Single Correct Answer)
+1
-0.3
For a product, the forecast and the actual sales for December $$2002$$ were $$25$$ and $$20$$ respectively. If the exponential smoothing constant $$(\alpha )$$ is taken as $$0.2,$$ then forecast sales for January $$2003$$ would be
A
$$21$$
B
$$23$$
C
$$24$$
D
$$27$$
4
GATE ME 2004
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT$$ analysis a critical activity has
A
maximum Float
B
zero Float
C
maximum Cost
D
minimum Cost
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12