1
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
A maintenance service facility has Poisson arrival rates, negative exponential service time and operates on a ‘first come first served’ queue discipline. Breakdowns occur on an average of $$3$$ per day with a range of zero to eight. The maintenance crew can service an average of $$6$$ machines per day with a range of zero to seven. The mean waiting time for an item to be serviced would be
A
$${1 \over 6}$$ day
B
$${1 \over 3}$$ day
C
$$1$$ day
D
$$3$$ day
2
GATE ME 2004
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT$$ analysis a critical activity has
A
maximum Float
B
zero Float
C
maximum Cost
D
minimum Cost
3
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
There are two products P and Q with the following characteristics GATE ME 2004 Industrial Engineering - Inventory Control Question 23 English

The economic order quantity (EOQ) of products P and Q will be in the ratio.

A
$$1:1$$
B
$$1:2$$
C
$$1:4$$
D
$$1:8$$
4
GATE ME 2004
MCQ (Single Correct Answer)
+2
-0.6
A compacting machine shown in the figure below is used to create a desired thrust force by using a rack and pinion arrangement. The input gear is mounted on the motor shaft. The gears have involutes teeth of $$2$$ $$mm$$ module. GATE ME 2004 Machine Design - Design of Spur Gears Question 13 English

If the pressure angle of the rack is $${20^ \circ },$$ the force acting along the line of action between the rack and the gear teeth is

A
$$250$$ $$N$$
B
$$342$$ $$N$$
C
$$532$$ $$N$$
D
$$600$$ $$N$$