GATE ME 2004
MCQ (Single Correct Answer)
+1
-0.3
At a hydro electric power plant site, available head and flow rate are $$24.5$$ $$m$$ and $$10.1{m^3}/s$$ respectively. If the turbine to be installed is required to run at $$4.0$$ revolution per second ($$rps$$) with an overall efficiency of $$90\% $$, the suitable type of turbine for this site is _______________.
A
Francis
B
Kaplan
C
Pelton
D
Propeller