GATE ME 1998
MCQ (Single Correct Answer)
+1
-0.3
In inventory planning, extra inventory is unnecessarily carried to the end of the planning period when using one of the following lot size decision policies:
A
Lot – for – lot production
B
Economic Order Quantity $$(EOQ)$$ lot size
C
Period Order Quantity $$(POQ)$$ lot size
D
Part Period total cost balancing
2
GATE ME 1998
MCQ (Single Correct Answer)
+1
-0.3
Which one of the following forecasting techniques is not suited for making forecasts for planning production schedules in the short range?
A
Moving average
B
Exponential moving average
C
Regression analysis
D
Delphi
3
GATE ME 1998
Subjective
+5
-0
A job shop has $$6$$ orders to be completed by a single turning center. The processing times and due dates are as follows: GATE ME 1998 Industrial Engineering - Scheduling Question 1 English

Assume that all orders are ready for processing. Give a production schedule that minimizes the average flow time. Compare this schedule with one that minimizes tardiness (lateness).

4
GATE ME 1998
MCQ (Single Correct Answer)
+1
-0.3
Which theory of failure will you use for aluminium components under steady loading is
A
principal stress theory
B
principal strain theory
C
strain energy theory
D
maximum shear stress theory