1
GATE ME 2016 Set 2
Numerical
+1
-0
In a single-channel queuing model, the customer arrival rate is $$12$$ per hour and the serving rate is $$24$$ per hour. The expected time that a customer is in queue is _______ minutes.
Your input ____
2
GATE ME 2016 Set 2
Numerical
+2
-0
A project consists of $$14$$ activities, $$A$$ to $$N$$. The duration of these activities (in days) are shown in brackets on the network diagram. The latest finish time (in days) for node $$10$$ is _____________ GATE ME 2016 Set 2 Industrial Engineering - Pert and Cpm Question 10 English
Your input ____
3
GATE ME 2016 Set 2
MCQ (Single Correct Answer)
+1
-0.3
For the brake shown in the figure, which one of the following is TRUE? GATE ME 2016 Set 2 Machine Design - Design of Brakes and Clutches Question 20 English
A
Self energizing for clockwise rotation of the drum
B
Self energizing for anti-clockwise rotation of the drum
C
Self energizing for rotation in either direction of the drum
D
Not of the self energizing type
4
GATE ME 2016 Set 2
Numerical
+1
-0
The force $${F_1}$$ and $${F_2}$$ in a brake band and the direction of rotation of the drum are as shown in the figure. The coefficient of friction is $$0.25.$$ The angle of wrap is $$3\pi /2$$ radians. It is given that $$R=1$$ $$m$$ and $${F_2} = 1N.$$ The torque (in $$N-m$$) exerted on the drum is ____________ GATE ME 2016 Set 2 Machine Design - Design of Brakes and Clutches Question 21 English
Your input ____