1
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
If the demand for an item is doubled and the ordering cost halved, the economic order quantity
A
remains unchanged
B
increases by a factor of $$\sqrt 2 $$
C
is doubled
D
is halved
2
GATE ME 1995
Subjective
+5
-0
A project with the following data is to be implemented: GATE ME 1995 Industrial Engineering - Pert and Cpm Question 7 English

(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.

3
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
In $$PERT,$$ the distribution of activity times is assumed to be
A
Normal
B
Gamma
C
Beta
D
Exponential
4
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is
A
$$4$$
B
$$8$$
C
$$16$$
D
$$24$$