A project with the following data is to be implemented: GATE ME 1995 Industrial Engineering - Pert and Cpm Question 4 English

(a) What is the minimum duration of the project?
(b) Draw a Gantt chart for the early schedule
(c) Determine the peak requirement of money and the day on which it occurs in above schedule.

2
GATE ME 1995
Subjective
+2
-0
On the average $$100$$ customers arrive at a place each hour, and on the average the server can process $$120$$ customers per hour. What is the proportion of time the server is idle?
3
GATE ME 1995
MCQ (Single Correct Answer)
+1
-0.3
The manufacturing area of a plant is divided into four quadrants. Four machines have to located one in each quadrant. The total number of possible layouts is
A
$$4$$
B
$$8$$
C
$$16$$
D
$$24$$
4
GATE ME 1995
Subjective
+2
-0
GATE ME 1995 Industrial Engineering - Production Planning and Control Question 4 English