1
GATE EE 2025
Numerical
+2
-0
Using shunt capacitors, the power factor of a 3-phase, 4 kV induction motor (drawing 390 kVA at 0.77 pf lag) is to be improved to 0.85 pf lag. The line current of the capacitor bank, in $A$, is _________ (Round off to one decimal places)
Your input ____
2
GATE EE 2025
Numerical
+1
-0

The maximum percentage error in the equivalent resistance of two parallel connected resistors of $100 \Omega$ and $900 \Omega$ with each having a maximum $5 \%$ error is ____________\%. (Round off to nearest integer value)

Your input ____
3
GATE EE 2025
Numerical
+2
-0
In the Wheatstone bridge shown below, the sensitivity of the bridge in terms of change in balancing voltage $E$ for unit change in the resistance $R$, in $\mathrm{mV} / \Omega$, is _________ (round off to two decimal places) GATE EE 2025 Electrical and Electronics Measurement - Measurement of Resistance and A.C Bridges Question 1 English
Your input ____
4
GATE EE 2025
MCQ (Single Correct Answer)
+1
-0.33

The operating region of the developed torque ( $T_{\mathrm{em}}$ ) and speed ( $\omega$ ) of an induction motor drive is given by the shaded region OQRE in the figure. The load torque $\left(T_L\right)$ characteristic is also shown. The motor drive moves from the initial operating point O to the final operating point S . Which one of the following trajectories will take the shortes time?

GATE EE 2025 Electrical Machines - Induction Machines Question 2 English
A
$O-Q-R-S$
B
$\mathrm{O}-\mathrm{P}-\mathrm{S}$
C
$O-E-S$
D
$\mathrm{O}-\mathrm{F}-\mathrm{S}$
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12