During a power failure, a domestic household uninterruptible power supply (UPS) supplies AC power to a limited number of lights and fans in various rooms. As per a NewtonRaphson load-flow formulation, the UPS would be represented as a

A
Slack bus
B
PV bus
C
$P Q$ bus
D
PQV bus
2
GATE EE 2025
Numerical
+1
-0
Consider a distribution feeder, with $R / X$ ratio of 5 . At the receiving end, a 350 kVA load is connected. The maximum voltage drop will occur from the sending end to the receiving end, when the power factor of the load is __________ (round off to three decimal places).
Your input ____
3
GATE EE 2025
Numerical
+1
-0

The bus impedance matrix of a 3-bus system (in pu) is

$$ Z_{\text {bus }}=\left[\begin{array}{lll} j 0.059 & j 0.061 & j 0.038 \\ j 0.061 & j 0.093 & j 0.066 \\ j 0.038 & j 0.066 & j 0.110 \end{array}\right] $$

A symmetrical fault (through a fault impedance of $j 0.007$ p.u.) occurs at bus 2 . Neglecting pre-fault loading conditions, the voltage at bus 1 , during the fault is __________ p.u. (round off to three decimal places).

Your input ____
4
GATE EE 2025
MCQ (Single Correct Answer)
+2
-0.67

In the system shown below, the generator was initially supplying power to the grid. A temporary LLLG bolted fault occurs at F very close to circuit breaker-1. The circuit breakers open to isolate the line. The fault self-clears. The circuit breakers reclose and restore the line. Which one of the following diagrams best indicates the rotor accelerating and decelerating areas?

GATE EE 2025 Power System Analysis - Power System Stability Question 1 English
A
Fig. (i) GATE EE 2025 Power System Analysis - Power System Stability Question 1 English Option 1
B

Fig. (ii)

GATE EE 2025 Power System Analysis - Power System Stability Question 1 English Option 2
C
Fig. (iii) GATE EE 2025 Power System Analysis - Power System Stability Question 1 English Option 3
D
Fig. (iv) GATE EE 2025 Power System Analysis - Power System Stability Question 1 English Option 4
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12