A project consists of $$7$$ activities. The network along with the time durations (in days) for various activities is shown in the figure. GATE ME 2015 Set 2 Industrial Engineering - Pert and Cpm Question 10 English

The minimum time (in days) for completion of the project is _____________

Your input ____
2
GATE ME 2015 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Sales data of a product is given in the following table: GATE ME 2015 Set 2 Industrial Engineering - Forecasting Question 11 English

Regarding forecast for the month of June, which one of the following statements is TRUE?

A
Moving average will forecast a higher value compared to regression.
B
Higher the value of order $$N,$$ the greater will be the forecast value by moving average.
C
Exponential smoothing will forecast a higher value compared to regression.
D
Regression will forecast a higher value compared to moving average.
3
GATE ME 2015 Set 2
Numerical
+2
-0
A manufacturer has the following data regarding a product:
Fixed cost per month $$=$$ Rs. $$50,000$$
Variable cost per unit $$=$$ Rs. $$200$$
Selling price per unit $$=$$ Rs. $$300$$
Production capacity $$=$$ $$1500$$ units per month

If the production is carried out at $$80\% $$ of the rated capacity, then the monthly profit (in Rs.) is ______________

Your input ____
4
GATE ME 2015 Set 2
Numerical
+1
-0
The uniaxial yield stress of a material is $$300$$ $$MPa.$$ According to Von mises criterion, the shear yield stress $$(in$$ $$MPa)$$ of the material is ___________.
Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12