1
GATE ME 2015 Set 2
MCQ (Single Correct Answer)
+2
-0.6
A balanced counter-flow heat exchanger has a surface area of $$20\,\,{m^2}$$ and overall heat transfer coefficient of $$20$$ $$W/{m^2}$$-$$K$$. Air $$\left( {{C_p} = 1000J/kg - K} \right)$$ entering at $$0.4$$ $$kg/s$$ and $$280$$ $$K$$ is to preheated by the air leaving the system at $$0.4$$ $$kg/s$$ and $$300$$ $$K.$$ The outlet temperature (in $$K$$) of the preheated air is
A
$$290$$
B
$$300$$
C
$$320$$
D
$$350$$
2
GATE ME 2015 Set 2
Numerical
+1
-0
Annual demand of a product is $$50,000$$ units and the ordering cost is Rs. $$7,000$$ per order. Considering the basic economic order quantity model, the economic order quantity is $$10,000$$ units. When the annual inventory cost is minimized, the annual inventory holding cost (in Rs.) is ___________
Your input ____
3
GATE ME 2015 Set 2
Numerical
+2
-0
A project consists of $$7$$ activities. The network along with the time durations (in days) for various activities is shown in the figure. GATE ME 2015 Set 2 Industrial Engineering - Pert and Cpm Question 10 English

The minimum time (in days) for completion of the project is _____________

Your input ____
4
GATE ME 2015 Set 2
MCQ (Single Correct Answer)
+1
-0.3
Sales data of a product is given in the following table: GATE ME 2015 Set 2 Industrial Engineering - Forecasting Question 11 English

Regarding forecast for the month of June, which one of the following statements is TRUE?

A
Moving average will forecast a higher value compared to regression.
B
Higher the value of order $$N,$$ the greater will be the forecast value by moving average.
C
Exponential smoothing will forecast a higher value compared to regression.
D
Regression will forecast a higher value compared to moving average.
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12