The precedence relations and durations of jobs in a project are given below: GATE ME 2002 Industrial Engineering - Pert and Cpm Question 1 English
(a) Draw the activity-on-arc project network
(b) Determine all critical path(s) and their duration(s).
(c) What is the total float for jobs $$B$$ and $$D?$$
2
GATE ME 2002
MCQ (Single Correct Answer)
+1
-0.3
A regression model is used to express a variable $$Y$$ as a function of another variable $$X.$$ this implies that
A
There is a causal relationship between $$Y$$ and $$X$$
B
A value of $$X$$ may be used to estimate a value of $$Y$$
C
Values of $$X$$ exactly determine values of $$Y$$
D
There is no causal relationship between $$Y$$ and $$X$$
3
GATE ME 2002
MCQ (Single Correct Answer)
+2
-0.6
Arrivals at a telephone booth are considered to be Poisson, with an average time of $$10$$ minutes between successive arrivals. The length of a phone call is distributed exponentially with mean $$3$$ minutes. The probability that an arrival does not have to wait before service is
A
$$0.3$$
B
$$0.5$$
C
$$0.7$$
D
$$0.9$$
4
GATE ME 2002
Subjective
+5
-0
A furniture manufacturer produces chairs and tables. The wood-working department is capable of producing $$200$$ chairs or $$100$$ tables or any proportionate combinations of these per week. The weekly demand for chairs and tables is limited to $$150$$ and $$80$$ units respectively. The profit from a chair is Rs.$$100$$ and that from a table is Rs.$$300.$$

$$(a)$$ Set up the problem as a Linear Program
$$(b)$$ Determine the optimum product mix for maximizing the profit.
$$(c)$$ What is the maximum profit?
$$(d)$$ If the profit of each table drops to Rs.200 per unit, what is the optimal mix and profit?

EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12