1
GATE ME 2002
MCQ (Single Correct Answer)
+1
-0.3
Trepanning is performed for
A
finishing a drilled hole
B
producing a large hole without drilling
C
truing a hole for alignment
D
enlarging a drilled hole
2
GATE ME 2002
MCQ (Single Correct Answer)
+2
-0.6
The time taken to drill a hole though a $$25$$ $$mm$$ thick plate with the drill rotating at $$300$$ $$rpm$$ and moving at a feed rate of $$0.25$$ $$mm$$/revolution is
A
$$10$$ $$sec$$
B
$$20$$ $$sec$$
C
$$60$$ $$sec$$
D
$$100$$ $$sec$$
3
GATE ME 2002
MCQ (Single Correct Answer)
+1
-0.3
In blanking operation the clearance is provided on
A
The die
B
The punch
C
Both die and punch equally
D
Neither the punch nor the die
4
GATE ME 2002
MCQ (Single Correct Answer)
+1
-0.3
Machining of complex shapes on $$CNC$$ machines requires
A
simultaneous control of $$x, y, $$ and $$z$$ axes
B
simultaneous control of $$x,$$ and $$y$$ axes
C
independent control of $$x$$ and $$Y$$ axes
D
independent control of $$x, y$$ and $$z$$ axes
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE