1
GATE EE 2022
MCQ (Single Correct Answer)
+1
-0.33

The valid positive, negative and zero sequence impedances (in p.u.), respectively, for a 220 kV, fully transported three-phase transmission line, from the given choices are

A
1.1, 0.15 and 0.08
B
0.15, 0.15 and 0.35
C
0.2, 0.2 and 0.2
D
0.1, 0.3 and 0.1
2
GATE EE 2022
Numerical
+1
-0
If only 5% of the supplied power to a cable reaches the output terminal, the power loss in the cable, in decibels, is ______. (round off to nearest integer).
Your input ____
3
GATE EE 2022
MCQ (Single Correct Answer)
+2
-0.67

The fuel cost functions in rupees/hour for two 600 MW thermal power plants are given by

Plant 1 : C1 = 350 + 6P1 + 0.004P$$_1^2$$

Plant 2 : C2 = 450 + aP2 + 0.003P$$_2^2$$

where P1 and P2 are power generated by plant 1 and plant 2, respectively, in MW and a is constant. The incremental cost of power ($$\lambda$$) is 8 rupees per MWh. The two thermal power plants together meet a total power demand of 550 MW. The optimal generation of plant 1 and plant 2 in MW, respectively, are

A
200, 350
B
250, 300
C
325, 225
D
350, 200
4
GATE EE 2022
Numerical
+2
-0

Two generating units rated for 250 MW and 400 MW have governor speed regulations of 6% and 6.4%, respectively, from no load to full load. Both the generating units are operating in parallel to share a load of 500 MW. Assuming free governor action, the load shared in MW, by the 250 MW generating unit is ________. (round off to nearest integer).

Your input ____
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12