1
GATE EE 2012
MCQ (Single Correct Answer)
+2
-0.6
In the circuit shown, an ideal switch $$S$$ is operated at $$100$$ $$kHz$$ with a duty ratio of $$50%$$. Given that $$\Delta {i_c}$$ is $$1.6$$ $$A$$ peak-to-peak and $${{\rm I}_0}$$ is $$5 A$$ $$dc,$$ the peak current in $$S$$ is GATE EE 2012 Power Electronics - Choppers and Commutation Techniques Question 31 English
A
$$6.6$$ $$A$$
B
$$5.0$$ $$A$$
C
$$5.8$$ $$A$$
D
$$4.2$$ $$A$$
2
GATE EE 2012
MCQ (Single Correct Answer)
+2
-0.6
In the $$3$$-phase inverter circuit shown, the load is balanced and the gating scheme is $${180^ \circ }$$ -conduction mode. All the switching devices are ideal. GATE EE 2012 Power Electronics - Inverters Question 16 English

The $$rms$$ value of load phase voltage is

A
$$106.1$$ $$V$$
B
$$141.4$$ $$V$$
C
$$212.2$$ $$V$$
D
$$282.8$$ $$V$$
3
GATE EE 2012
MCQ (Single Correct Answer)
+1
-0.3
The bus admittance matrix of a three-bus three-line system is
$$y = j\left[ {\matrix{ { - 13} & {10} & 5 \cr {10} & { - 18} & {10} \cr 5 & {10} & { - 13} \cr } } \right]$$
If each transmission line between the two buses is represented by an equivalent $$\pi \,$$ network, the magnitude of the shunt susceptance of the line connecting bus $$1$$ and $$2$$ is
A
$$4$$
B
$$2$$
C
$$1$$
D
$$0$$
4
GATE EE 2012
MCQ (Single Correct Answer)
+1
-0.3
The figure shows a two-generator system supplying a load of $${P_D} = 40\,MW,$$ connected at bus $$2.$$ GATE EE 2012 Power System Analysis - Power Generation Cost Question 19 English

The fuel cost of generators $${G_1}$$ and $${G_2}$$ are: $${C_1}\left( {{P_{G1}}} \right) = 10,000\,\,Rs/MWhr$$ and $${C_2}\left( {{P_{G2}}} \right) = 12,500\,\,Rs/MWhr$$ and the loss in the line is $$\,{P_{loss(pu)}} = 0.5\,\,P_{G1\left( {pu} \right),}^2\,\,\,\,$$ where the loss coefficient is specified in pu on a $$100$$ $$MVA$$ base. The most economic power generation schedule in $$MW$$ is

A
$${P_{G1}} = 20,\,{P_{G2}} = 22$$
B
$${P_{G1}} = 22,\,{P_{G2}} = 20$$
C
$${P_{G1}} = 20,\,{P_{G2}} = 22$$
D
$${P_{G1}} = 0,\,{P_{G2}} = 40$$