1
GATE EE 1995
MCQ (Single Correct Answer)
+1
-0.3
The surge impedance of a $$400$$ km long overhead transmission line is $$400$$ $$\Omega $$. For a $$200$$ km length of the same line, the surge impedance will be
A
$$200$$$$\Omega $$
B
$$800$$ $$\Omega $$
C
$$400$$ $$\Omega $$
D
$$100$$ $$\Omega $$
2
GATE EE 1995
Fill in the Blanks
+2
-0
The rated load of an underground cable is always _______its natural load.
3
GATE EE 1995
MCQ (Single Correct Answer)
+1
-0.3
In order to have a lower cost of electrical energy generation,
A
The load factor and diversity factor should be low
B
The load factor should be low but diversity factor should be high
C
The load factor should be high but diversity factor should be low
D
The load factor and diversity factor should be high
4
GATE EE 1995
Fill in the Blanks
+1
-0
The positive sequence component of the voltage at the point of fault in a power system is zero for a _________fault.
EXAM MAP
Medical
NEETAIIMS
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
Civil Services
UPSC Civil Service
Defence
NDA
Staff Selection Commission
SSC CGL Tier I
CBSE
Class 12