1
GATE ME 2014 Set 4
MCQ (Single Correct Answer)
+2
-0.6
The precedence relations and duration (in days) of activities of a project network are given in the table. The total float (in days) of activities $$e$$ and $$f,$$ respectively, are GATE ME 2014 Set 4 Industrial Engineering - Pert and Cpm Question 10 English
A
$$0$$ and $$4$$
B
$$1$$ and $$4$$
C
$$2$$ and $$3$$
D
$$3$$ and $$1$$
2
GATE ME 2014 Set 4
Numerical
+2
-0
At a work station, $$5$$ jobs arrive every minute. The mean time spent on each job in the work station is $$1/8$$ minute. The mean steady state number of jobs in the system is __________
Your input ____
3
GATE ME 2014 Set 4
Numerical
+2
-0
A shaft is subjected to pure torsional moment. The maximum shear stress developed in the shaft is $$100$$ $$MPa.$$ The yield and ultimate strengths of the shaft material in tension are $$300$$ $$MPa$$ and $$450$$ $$MPa,$$ respectively. The factor of safety using maximum distortion energy (Von - Mises) theory is __________.
Your input ____
4
GATE ME 2014 Set 4
Numerical
+2
-0
A bolt of major diameter $$12$$ $$mm$$ is required to clamp two steel plates. Cross sectional area of the threaded portion of the bolt is $$84.3$$ $$m{m^2}$$ . The length of the threaded portion in grip is $$30$$ $$mm,$$ while the length of the unthreaded portion in grip is $$8$$ $$mm.$$ Young's modulus of material is $$200$$ $$GPa.$$ The effective stiffness (in $$MN/m$$) of the bolt in the clamped zone is _______.
Your input ____
EXAM MAP
Medical
NEET
Graduate Aptitude Test in Engineering
GATE CSEGATE ECEGATE EEGATE MEGATE CEGATE PIGATE IN
CBSE
Class 12